
Phase 1 Budget
Phase 1 Detailed Budget Restoration and Infrastructure
Total Project Cost: $15,157,600 | Phase 1 Budget: $1,757,600
Timeline: April 2026 – January 2027 (10 months)
​
Budget Overview
​
Following a comprehensive review of prior project documentation and current 2026 market data for the Chicago/Riverdale area (historic restoration, MEP upgrades, BESS systems, security, and A/E services), the Phase 1 budget has been refined with tighter, data-backed estimates.
​
These refinements maintain the fixed total of $1,757,600 while shifting allocations slightly for realism: heavier weighting toward envelope and MEP due to post-2023 storm damage and code requirements, with modest contingency buffers. The refined breakdown supports rapid stabilization, full weather-tight protection, resilient infrastructure, and activation of the 13,594 sq ft Empower Skills Training Wing by January 2027 for early training revenue.
Phase 1 Budget Allocation
Total Phase 1 Budget: $1,757,600 (100%)
​
Breakdown by Major Deliverable (with supporting rationale and 2026 market ranges):
​
-
Building Envelope Restoration (full weather-tight envelope: roofs, walls, windows, doors – priority for historic asset protection and storm damage remediation) Refined Allocation: $685,000 (~39%)
​
Detailed Allocation: $685,000 (39.0%)
​
-
Roof replacement & repairs (multi-building historic scope): $320,000
-
Exterior wall/masonry restoration & sealing (storm damage remediation): $185,000
-
Window & door restoration/replacement (historic-compatible, energy-efficient): $140,000
-
Flashing, gutters, sealing & miscellaneous envelope: $40,000
​​
Rationale: Chicago-area historic/commercial roof replacement averages $6–$18/sq ft (asphalt/metal); full envelope (roof + walls + fenestration) for a multi-building campus typically runs $150–$300+/sq ft for complex restoration. Allocation prioritizes weather-tight integrity first to prevent further deterioration.
​​
-
MEP Infrastructure & BESS (complete replacement of electrical, water/sewer, resilient fiber systems + 250 kW / 500 kWh Battery Energy Storage System) Refined Allocation: $615,000 (~35%)
Detailed Allocation: $615,000 (35.0%)
​
-
Electrical systems (full replacement & code compliance): $210,000
-
Water & sewer systems (full replacement): $145,000
-
Resilient fiber optic & communications infrastructure: $65,000​
-
250 kW / 500 kWh BESS (hardware, installation, integration & commissioning): $195,000
​
Rationale: MEP systems in gut-level historic renovations range $100–$250+/sq ft in Chicago; commercial BESS installed costs average $360–$690/kWh (mid-range ~$500–$550/kWh selected for 500 kWh capacity yields ~$250K–$275K hardware + installation/integration). Combined allocation reflects full utility replacement plus energy resilience for code compliance and long-term reliability.
​
-
Historic Church Oratory Conversion (new flooring, MEP systems, interior restoration of the historic church space) Refined Allocation: $225,000 (~13%)
Detailed Allocation: $225,000 (12.8%)
​
-
New flooring installation (durable, code-compliant): $85,000
-
Targeted MEP integration (lighting, HVAC tie-ins, plumbing): $75,000
-
Interior finishes & historic restoration elements: $45,000
-
Fixtures, millwork & final fit-out: $20,000
Rationale: Church/oratory adaptive reuse and interior fit-out typically $180–$300+/sq ft for historic spaces; focused scope (flooring + targeted MEP + finishes) keeps costs controlled while activating a key community asset.
​​
-
Security & Site Protection (perimeter security fencing + 9 months of overnight security services) Refined Allocation: $132,600 (~7.5%)
Detailed Allocation: $132,600 (7.5%)
​
-
Perimeter security fencing (commercial-grade chain link/steel, installed): $52,600
-
Overnight security services (9 months, 12-hour shifts, 7 days/week): $80,000
Rationale: Commercial security fencing in Illinois averages $8–$25/linear ft installed; overnight unarmed security services $15–$30/hour. 9-month coverage plus perimeter installation provides full site safeguarding during and post-construction.
​​
-
Architecture, Engineering & Permitting Services (comprehensive A/E services and full permitting) Refined Allocation: $100,000 (~5.7%)
Detailed Allocation: $100,000 (5.7%)
​
-
Architectural & engineering design services: $72,000
-
Structural/mechanical/electrical engineering coordination: $18,000
-
Permitting, inspections & regulatory compliance: $10,000
Rationale: Historic renovation A/E fees typically 7–15% of hard costs (lower end applied here for efficiency); includes all design, engineering coordination, and regulatory approvals to ensure seamless code compliance.
​​
Total: $1,757,600
Embedded Contingency: $210,000 (~12% across all categories) – allocated proportionally for weather delays, material escalation, or hidden storm damage typical in 2023-damaged historic sites.
​
Budget Summary & Key Drivers
​
-
Phase 1 Total Investment: $1,757,600 (~11.6% of full $15.157M campus)
-
Hard Costs (Envelope + MEP/BESS + Oratory + Security): $1,557,600 (88.6%)
-
Soft Costs (A/E & Permitting): $100,000 (5.7%)
-
Contingency: $210,000 (12%) – standard for post-storm historic restoration
-
Primary Cost Drivers: Envelope (39%) and MEP/BESS (35%) – critical for immediate safety, code compliance, and energy resilience
-
Market Alignment: Calibrated to April 2026 Chicago/Riverdale conditions, including labor rates, historic preservation premiums (15–25% uplift), and resilient infrastructure benchmarks
-
Projected Early ROI: Operational Empower Skills Training Wing by January 2027 generates initial workforce development and corporate training revenue to support seamless transition into Phase 2 (February 2027).
​​
Alignment with Overall Project & Risk Mitigation
​
This $1,757,600 investment delivers:
​
-
Fully secured, weather-tight, code-compliant campus​
-
Resilient 250 kW / 500 kWh BESS and modern utilities​​
-
Protected historic assets ready for education, health, and eventual boutique hotel phases
Risk Mitigation:
​
-
12% contingency for weather/supply chain issues​
-
Performance bonds and early permitting engagement​​
-
Aggressive 10-month schedule with built-in buffers
​​
Transition to Phase 2
​
Phase 1 completion in January 2027 directly hands over a stabilized, infrastructure-ready campus for immediate launch of school restorations, training programs, and enrollment of 500+ participants in February 2027.